Active Projects
tinson Avenue Overlay and Intersection Improvements
ALERT: A 10-day full closure of the Stinson/Rosedale intersection is in effect from Wednesday, April 21st thru Friday, April 30th. A map of the full closure is shown here. Please use alternate routes. A law enforcement officer or flaggers will direct traffic at the intersection of Pioneer and Harborview to assist pedestrians and motorists during peak traffic times.
Project Description
Construction work for the Stinson Ave. project commenced on March 29, 2021 and will continue into the summer. The project will construct a new compact roundabout at the Rosedale/Stinson intersection, reconstruct the intersection at Grandview/Stinson, pedestrian improvements along Stinson Ave., and a pavement overlay on Stinson from Grandview St. to Rosedale St.
Significant delays are expected in the downtown Gig Harbor corridor. The public is advised to use alternate routes whenever possible. Roadway closures for the project will occur in multiple phases.
We appreciate your patience during the construction of this project.
Current Project Schedule
- 10-day FULL CLOSURE of the Stinson/Rosedale Intersection will take place from April 21st thru April 30th. Detour routes will be posted. A law enforcement officer or flaggers will direct traffic at the intersection of Pioneer and Harborview to assist pedestrians and motorists during peak traffic times.
- Construction start date March 29, 2021 with completion anticipated by late summer 2021.
- All work is weather dependent.
Primary Project Contacts
Laura Pettitt, Tourism & Communications Director at 253-853-3554 or by email at communications@gigharborwa.gov
Kyle Neiman, Construction Supervisor at 253-853-7607
__________________________________________________________________________________________
38th Avenue Improvements Phase 1 Project
Project Description:
The city is working with the consultant David Evans and Associates to finalize design work on a capital improvement project along the east side of 38th Avenue. The limits of this project are from Briarwood Lane to the southerly city limits. The work generally consists of incorporating Low Impact Development Standards (LID) for a bike lane, sidewalk, biofiltration swale, and pedestrian lighting. This project includes the first phase of improvements to provide pedestrian safety in City limits leading to two schools located just outside City limits. A grant from the Department of Ecology reimbursed some of the design costs.
Project Schedule
- Pending
Primary Project Contact
Marcos McGraw, Project Engineer at mcgrawm@cityofgigharbor.net
__________________________________________________________________________________________
Burnham Drive & Harborview Drive ½-width Roadway Improvements Project - Design and Permiting
Project Description
The City is working with consultant David Evans and Associates in completing the preliminary design and permitting associated with street improvements along Burnham Drive in compliance with City of Gig Harbor Public Works Standards. The project consists of adding bike lanes, sidewalk, planter strip, and pedestrian lighting on the east side of the roadway between Austin Street and Harbor Hill Drive. It also includes incorporating LID stormwater elements to reduce runoff, providing flow control, and providing stormwater quality treatment.
Project Schedule
- Pending
Primary Project Contact
Marcos McGraw, Project Engineer at mcgrawm@cityofgigharbor.net
__________________________________________________________________________________________
Lift Station #6 Replacement - Ryan Street
Project Description
Replacement of the underground lift station at the existing site.
Project Schedule
- Virtual Open House held: 9/16/20 from 4:00 pm - 5:30 pm.
- Final design and permitting underway
- Construction planned for early summer 2021 with completion anticipated by the end of 2021
Primary Project Contact
Trent Ward, PE, City Engineer at wardt@cityofgigharbor.net